Kit ErectionA third trailer has arrived and delivered most of the wooden parts. The final trailer will include the factory painted windows and doors. Progress is very good despite the poor weather and early darkness.
| ||
![]() 1. Laying out the Logs. Note the exceptional design of the Ball Notch which results in a very tight frame and excellent resistence to the Irish weather. |
![]() 2. The Log Frame is underway and the ground floor layout becomes apparent. |
![]() 3. Sledge hammers encourage the Logs into place. |
![]() 4. Window and door positions are evident and the smaller Logs are easier to manage. Until we get above the window height. |
![]() 5. Construction moves to the second floor. |
![]() 6. The intermediate floor joists are laid. |
![]() 7. The log frame is completed ten days after the kit is unloaded. |
![]() 8. The massive laminated beams are in place. |