This phase of activity marks the start of real construction work on your site
and a Commencement Notice must be filed with your local authority to mark this
event.
Depending on the recommendations of your engineer, a series of activities will
get underway usually starting with Site Preparation including site clearance,
preparation of a temporary roadway for access to the site, drainage and
installation of the septic tank or treatment system.
An electrical supply is
needed on site so the ESB should be given plenty of notice to provide a
"Builder's Supply" electrical installation or you may have a friendly
neighbour who can provide a heavy duty extension cable. Alternatively a
generator can be used.
Your engineer will recommend a particular type of
foundation (e.g. Strip, Pier, Ventilated Strip or Raft/Slab) and your selected local builder
will build the foundations to their specification. Our kit
price includes the production of the foundation plans which give detailed layout
measurements.
Our log homes do not have any special
foundation requirements and the same foundations can be used as would be used
for a block house. In general, we recommend that the base be built at
least 60cm above the ground to protect the base logs from large puddles.
In some parts of Ireland a Radon barrier must be used in the foundations to
prevent build-up of harmful Radon gas.
Our specific Foundations Services available to you are:
FND01 - Provision of detailed foundation and construction drawings for
your log kit (included in the Kit Supply service)
|